Photographs

 

Signing of the Contract

John Morrison and Peter Scholtz for the church and  Paul Foster from our contractor Paul Foster Interiors signing the contract.

Work has already started and is due to be completed by 15th October.

End of Week 1

Under 5s huts have been dismantled and scaffold erected ready for the demolition of the vestry. This is due to start on Monday 26th April when work to create a temporary disabled toilet is also due to commence.

 

 

 

 

End of Week 2

The site has now been cleared, an access road laid, walls and a brick shed have been demolished, and the slates have been removed from the vestry roof.

End of Week 3

The bases for the Under 5’s and Property Steward’s huts have now been installed and on the left is the stack of cleaned bricks ready for the garden walls.

End of Week 4

Placing of the hardcore for the hall floor has started.